首页-新闻资讯-钢板桩施工中可能出现问题的解决方法!

新闻资讯

来源:http://www.jnlsgbz.com/ 日期:2020-06-02 发布人:lasen
  钢板桩在施工的过程中出现一些问题是在所难免的,关键是我们能了解问题的根源所在,并且能及时的解决这个问题,下面钢板桩施工租赁的小编就来简单向大家介绍下钢板桩施工时可能出现的问题及其解决的方法,希望对大家能有所帮助。
  In the construction process of steel sheet pile, some problems are inevitable. The key is that we can understand the root of the problem and solve it in time. The following small compilation of professional steel sheet pile construction lease will briefly introduce the possible problems and solutions during the construction of steel sheet pile, hoping to help you.
  1倾斜。产生这种问题的原因是被打桩与邻桩锁口间阻力较大,而打桩行进方向的贯入阻力小;
  1 tilt. The reason for this problem is that the resistance between the driven pile and the adjacent pile lock is large, while the penetration resistance in the driving direction is small;
  处理方法:施工过程中用仪器随时检查、控制、纠正;发生倾斜时用钢丝绳拉住桩身,边拉边打,逐步纠正;对先打的板桩适度预留偏差。
                钢板桩施工租赁
  Treatment method: use instruments to check, control and correct at any time during the construction process; use steel wire rope to hold the pile body in case of inclination, while pulling and driving, and gradually correct; properly reserve deviation for the first driven sheet pile.
  2扭转。产生该问题的原因:锁口是铰式连接;
  2 twist. The reasons for this problem are: the lock mouth is hinged connection;
  处理方法:在打桩行进方向用卡板锁住板桩的前锁口;在钢板桩之间的两边空隙内,设滑轮支架,制止板桩下沉中的转动;在两块板桩锁口搭扣处的两边,用垫铁和木榫填实。
  Treatment method: lock the front lock of sheet pile with clamp plate in the driving direction; set pulley bracket in the gap between the two sides of sheet pile to prevent the rotation of sheet pile during sinking; fill the two sides of the buckle of the lock of sheet pile with pad iron and wooden tenon.
  3共连。产生的原因:钢板桩倾斜弯曲,使槽口阻力增加;
  3 in total. The causes are as follows: the steel sheet pile is inclined and bent, which makes the notch resistance increase;
  处理方法:发生板桩倾斜及时纠正;把相邻已打好的桩用角铁电焊临时固定。
  Treatment method: timely correct the inclination of sheet pile; temporarily fix the adjacent piles with angle iron welding.
  以上三个方面的问题,一般施工方可能会经常遇到,出现这样的问题时大家应当及时的按照以上方法来解决问题,这样工程人员安全有保证,工程才能按时按质完工。想要了解更多内容,欢迎大家咨询钢板桩施工租赁http://www.jnlsgbz.com官网。
  Generally, the construction party may often encounter the problems in the above three aspects. In case of such problems, we should timely solve the problems according to the above methods, so that the safety of engineering personnel can be guaranteed, and the project can be completed on time and with quality. To learn more, welcome to consult the professional steel sheet pile construction leasing http://www.jnlsgbz.com Official website.